Rambler Mine Tailing Pond

L&B Electric Ltd.
Renewable Resources
Industrial
Automation
Project Management
Field Services
Transmission
Distribution
Electrical Engineering Studies
Hydro
Project Title: 
Rambler Metals & Mining, Baie Verte Peninsula, Newfoundland & Labrador, Design Control System for new Tailing Pond at existing Copper Ore processing plant.
Services We Provided: 
- Electrical Engineering Studies
- Design and Specifications
- Field Services
- Project Management
Project Description

Project involved the design and specification of a new PLC controller, development of interactive graphic page using VTScada software, responsibility for on-site testing and commissioning all new controls for tailings pond pump station at a Copper Processing plant, which included various water pumps, valves, and level and flow instrumentation.

Scope of Work

The specific scope of the project included the following elements:

  • Designed the PLC control system for the new tailings pond pump equipment, including electrical schematics.
  • Programmed the PLC to operate in manual or automatic mode and to communicate with the VTScada HMI software.
  • Designed the HMI graphic screen for the tailings pond, including popup windows for control functions of pumps and valves.
  • Tested and commissioned all analog and discrete data displayed on graphic screens as well as all control functions.