UpgradeProject involves the design, field testing and commissioning of new digital excitation systems associated a 27.5MVA, 6kV, 50Hz Francis Turbine at the DeerLake Generating Station. The project also involves the design, field testing and commissioning of new protective relay systems associated with the 66kV transmission lines between the Deer Lake Hydro Generating Station and Corner Brook Pulp and Paper in Corner Brook,NFLD.
The specific scope of the project includes the following elements: